Progress report. Newsletter no 13. To find out the works that have been completed this week and also ongoing works at the development at Bretonside.

McLaren Site Office:

Works completed this week include:

 Closure of footpath to viaduct completed.

 Tubosider attenuation tank installation ongoing.

 Retaining wall to RBS perimeter ongoing.

 SWW drainage to undercroft commenced.

CSR update with planned events:

 We will be delivering our second community site newsletter to local residents and businesses in March and holding a community drop in on site Thursday 8th March from 1-2pm.

 We will be holding a mini MOT health check for site operatives on March 5th .

 We will be hosting an open doors event with Building Plymouth on 19th March. 